Project overview:

REVIEW, FINAL DESIGN AND SUPERVISION FOR WASTEWATER NETWORKS IN DAIR AL BALAH AND JABALIA

 


Project start late 2014

Client:

PWA support agency:

Funded by: EU

Facilitated support:

Funding management:

Main Consultant:

Norplan parter
/sub-consultant , CEP

Page under construction

 

 

Satellite Photo showing Project Areas.

 

 

 

 

 

Project areas marked on Google Earth map covering Gaza.

 

 

 

 

Click enlarge for Amer Area

Click here to enlarge Al Berka Area




BRIEF PROJECT SUMMARY

Review and revise design for sewer network, prepare tendering documents, tendering and manage construction supervision for Amer and Al Berka areas. Approximately 25 km of main network has been planned. The networks are to be connected to two existing pumping stations in both areas.

Project start: November 2014 and scheduled duration of 21 months.
( 6 months planning/tendering + 15 months construction)

See separate pages for details



KEY ACTORS
 

Client: Palestinian Water Authority, - contact management/ approvals

Funding Agency: EU, with German Cooperation/ KEW managing funding.

CMWU: Technical management of client affairs on behalf of PWA.

Consultant: Norplan, Norway working with CEP, Gaza and sub consultant and partner.

See separate page for further details of actors.


CONTRACT DETAILS
 

Contract title:

Review, Final Design and Supervision for Wastewater Networks in Dair Al Balah and Jabalia.
  Funding: Europeen Commission though KFW
Address: Palmengartenstrasse 5-9, 60325, Frankfurt, Germany
Attn. Principal Dev. Manager, G.Grüner, georg.gruener@kfw.de, tel:+49 69 74319657
Delegation agreement, reference ENPI/2010/022-474, dated 10.12.2012 between the European Union, represented by the European Commission and KfW ("Delegation Agreement"),
  Benefactor organization: Palestine Water Authority, Gaza,
Wahda Street, Shaat Building, Gaza, Attn. Dir. Rebhi El Sheikh,
ralsheikh@pwa-gpmu.org, + 970 8 2827409,
  Consultant

NORPLAN, (Partner Asplan Viak AS)

Address: Kjørboveien 20, 1337 Sandvika, Norway, +47 417 99 417
Attn.; Dr. S. Stoveland, sst@asplanviak.no, tel:+47 91571225, (click for more details of project team)
Local partner: CEP, Gaza,
Attn Mohammad Ziara, cep@gmail.com
Contract commencement date: August 2014
Agreement no.: ENPI/2012/304-653.
Contracted sum; Euro: 352,569
  Contractor for Amer Area Handala Company of Engineering, Gaza
Attn. General Diectorr Eng. Farid Baroud
Address:2nd Floor, El Jala St. Gaza
Contract sum: Euro: 1,232,257
  Contrator at Al Berka area Zediah Company Ltd For trading and contracting
Attn. General director Eng. Alaa Zediah
Address: 9th Floor, Al Watan Building, Al Jalaa St. Gaza
Contract sum: Euro: 1,257,000


THE TARGET POPULATION:
Gaza City and urban area with 1.8 million people in need of water supply and wastewater management systems. Below a few photos highlights the urban area Gaza has developed into in great need of functional infrastructure development.
 
  Gaza city. Highly urbanised and densely populated.
 
  Main street north- south in Gaza From Jabalia area
 
  Rashid Road, the main road along the coast passing both project areas of Amer and Al Berka From Amer pumping station the wastewater is treated in a waste stabilization pond system waiting to be replaced by a newly constructed wastewater treatment plant , NGEST.

 

Web Master: Svein Stoveland, sst@asplanviak.no, tel +47 915 71 225. Please advise if problems or mistakes