Construction - Amer Area.

- Network layout
- Photos from construction progress ( latest phots on top)


Click on photo to view:

 

Street maps

Progress map

TABULAR ROAD CONSTRUCTION PROGRESS

Signboard

Street construction

Site office

Site inspection

 

 

FOR OVERVEIW: CONSTRUCTION PLANS FOR AMER:

 

Satellite photo of project area. Click to enlarge. Amer area including Beit Lahia and Jabalia

Street map , blue existing sewers, red lines new proposed sewers

Click to see overview of streets with construction in in progress or completed., (as 15th October 2016)


Progress
..March2017
Copmaction works of the trench at PS5, Jabalia, Amer area

 

Reinstatement works for the Interlock Tiles at PS5*, Jabalia, Amer area

PWA Site visit to R04A, Jabalia, Amer area



Progress
..Febrary 2017

Excavation and laying PVC-U pipes 250mm Dia at R31, Beit Lahai, Amer area

Watering the trench at R31, Beit Lahai, Amer area

Checking for the installed manhole by the project manager, B32 Beit Lahai, Amer area

Excavation and laying PVC-U pipes 200mm Dia. At B19 Beit Lahai, Amer area

Progress ..January 2017

Dewatering of Septic tanks at B33, Beit Lhaia, Amer Area

Backfilling works for the septic Tanks, R31, Biet Lahia, 16.01.2017

Excavation and compaction works, B18, Beit Lahia Area

Office meeting to discuss the works at Al Karama Area. Date: 24.01.2017
Presence from Left: Eng. Mohamed Abu Reyalla, Jabalia Municipality, Eng. Ahmed Kullab, PWA, Eng. Tawfik Hamad, PWA, Eng. Basim Sirdah, Norplan/CEP, Eng. Robin Al Mazloom, CMWU and Eng. Hamdi Moutier, Jabalia Municipality



Project Signboard at Amer
 




Field Inspections and Quality Control by consultant
15th Novermber 2016
Eng Utku from Norplan HQ inspects drawrings as oonstruted in the presence of Dir. M. Ziara, CEP Above, checking daily reports for content. Quite satisfactory with essential information and approproate signatures
Inspecting completed construction in Amer Area. with Mohammad Ziara, Eyad wa Wardu, , Basim Sirdah, Svein Stoveland and Utku Koz. About 50% of road nedwork completed and progress appears satisfactory.




Project news flash
.30th October 2016

Visit for Al Seksek PVC-U Factory (quality control visit). Presence: PWA: Eng. Ahmed Kullab, Eng. Nazek Rehan and Eng. Tawfik Hamad. CMWU: Eng. Motaz Abu Al Komboz. Norplan/CEP: Eng. Basim Sirdah. Contractor (Handalh Company): Eng. Adel Hammad. Al Seksek Factroy: Mr. Osama Al Fayomi, Eng. Date: 25.10.2016

Excavation works in road B05. Tob, above, laying new network in R 07, and fixing house connection in B10.


Construction works at R03, R12, R17, and R18A,
8th October 2016
Excavation and lying of 200mm PVC-U pipes at R17, Jabalia Excavation and lying of 200mm PVC-U pipes at R18A, Jabalia
Excavation and lying of 200mm PVC-U pipes at R12, Jabalia Lying of the tracer tape over the pipes at R12, Jabalia
Shuttering and steel reinforcement for the ground beams at Amer pumping station.

Inspection for the columns (axes and shuttering) by the engineer at Amer pump station

Excavation and laying PVC-U Pipes 450mm Dia. At R03, Jabalia area

Inspection for the concrete sewer manhole by the project manager in the presence of Eng. Ahmed Kullab (PWA), at R03, Jabalia area



Construction works at Road12
:20th September 2016
Excavation at R12 Installing concrete sewer manhole in position at R12




More construction in R42,
.. 7th September 2016
 
Excavation and laying 250 mm pipes, at R42 in th presence of the design Engineer Eyad Abu Warda. Excavation and laying pipes  



Construction in Road R16, R38 and R42
4th September 2016
Excavation and laying pipes (200) at R38 Excavation works at R42 Excavation, lying of pipes and compaction at R42
Compaction work for trench in R42 Watering for the backfilling at R42 Excavation and lying of 200mm pipe for R16






Construction in Road 16
: 27th August 2016
   
4 meter deep excavation requiring shuttering as can be seen on above left. Watering and compaction of trench bed in good progress.



Site Meeting 3rd August 2016

Meeting at Amer Office to discuss the project progress. Present from Left:( photo above left) Eng. Ibraheem El Halool (Norplan/CEP), Eng. Basim Sirdah (Norplan/CEP), Mr. Keith Brook (Norplan), Eng. Ahmed Kullab (PWA), Eng. Tawfik Hamad (PWA), Eng. Adel Hammad (Handala Company), Eng. Farid Barood (Handala Company), and Mr. Tahseen Deyab (Handala Company). >


Meetings with Municipalities
..date: 1st of August 2016

Meeting with Jabalia & Beit Lahiam Municipalities in order to discuss Amer Project Status. Present from left: Eng. Ahmed Shehada (Jabalia Municipality), Mr. Keith Brook (Norplan), Eng. Mouataz Abu Alkomboz (CMWU), Eng. Nazik Rehan (PWA), Eng. Ahmed Kullab (PWA), Eng. Tawfeek Hamad (PWA), Eng. Mohamed Khalaf (CMWU), Eng. Jaber Al Kasseh (Beith Lahia Municipality), and Eng. Mahmood Abu Samara (Beith Lahia Municipality).



Work progress on Road 01
..30th July 2016
Preparing works for cutting the Asphalt at R01 Determining the Alignment in the presence of the Engineer, R01
Cutting the Asphalt at R01 for Excavation Works Inspection for the Existing Manhole by the Project Manager and the Resident Engineer, R01. Date 30.07.2016.

Site Discussion at R01 Jabalia Area. Present from Left: Eng. Ibraheem El Halool (Norplan/CEP), Eng. Adel Hamad (Handalah Company), Mr. Tahseen Deyab (Handalah Company), Mr. Keith Brook (Norplan), Eng. Farid Barood (Handalah Company), Eng. Basim Sirdah (Norplan/CEP), and Eng. Ahmed Kullab (PWA). Date: 30.07.2016

Inspection the excavation Works by the Project Manager, R01.

Watering for the trench, R01.

Compaction Works for the Trench, R01.

Sand Cone test for the compaction works, R01.







Work progress on Road 14
..20th July 2016
Excavation in R15 Placing precast manhole in trench
Adjustment the Level of the Manhole Base at R15 Checking of the Manhole Level By the Engineer at R15
illustrating to the Technician in how to put the bedding under the pipes at R15. Inspection the Invert levels of pipes by the Engineer
Placing Lane concrete 5cm thick under the manhole base at R15. Warning sign for the public at R15


Progress Meeting at PWA offices
17th July 2015
 
 

Discussion the progress status for Amer & Berka Project at PWA office.
Presence from Left:  Eng. Nazek Rehan (PWA), Eng. Ahmed Kullab (PWA), Eng. Basim Sirdah (Norplan/CEP).



Testing PVC pipes
.. 14th July 2016
Testing PCV-U pipes at Ismalic University Lab. From right, Eng Basim Sirdah ( Norplan/CEP) and Eng Hytham Radwan ( Islamic UN. Lab) Testing PCV-U pipes at Ismalic University Lab. From left, Eng Basim Sirdah ( Norplan/CEP) and Eng Tawfic Hamad (PWA) and Eng Ahmed Kullabv ( PWA)


Sewer construction on Road 29
..date: 12th July 2016
Excavation in R29 One precast manhole being lowered into position (13/7/16
Water level checked on top of manhole at R29 by Engineer ( Basim Sirdah) Norplan/ CEP team there to check levels with Eng Basim Sirdah and Design engineer Eyad abu Warda




Inspecting Manhole at R33
: 9th July 2016
Checking the Benching works by Engineer Basim Sirdah at R33 ( left), and photo above ; benching works, final finish at R33.


Sewer construction on Road 37
: 4th July 2016
Adjustment the alignment of Pipelines at R37

Adjustment for the alignment of Pipelines at R37 ( photo above and below)

Site discussion by teamwork. From Left: Eng. Ashraf Odeh, Eng. Yasser Motair, Eng. Basim Sirdah, Mr. Kamal Al Malfooh, Eng. Eng. Ibraheem Al Halool.



Sewer construction on Road 44:
12th July 2016
 



Testing and supervision,
Roads 35 & 36: 19th June 2016
Hydrostatic test for the installed pipelines at R35
Excavation works at R36 Keith Brooke inspecting manhole


Testing
..date: 18th June
Preparing for Hydrostatic test at R36 Sand cone test for the backfilling works at R36
Excavation works at R21 ( above or Rasheed Street) Norplan/CEP field staff checking progress.
Adding water for better compaction


Site Offices
..date:
Site Engineer's office facilities provided by the contractor.
 
Office 2 Office 3 Hall Utility







Progress
, Road 33.: 15th June 2016
Warning Sign board at R33  
Deep Excavation Works at R21, (Rasheed Street)




Site meeting
date:14th June 2016

Site meeting and inspection:

From Left: Eng. Tawfic Hammad (PWA), Eng. Basim Sirdah (Norplan/CEP), Eng. Adel Hammad (Handala company), Eng. Farid Barood (Handala company), Eng. Ahmed Kullab (PWA), MR. Tahseen Deyab (Handala company), Eng. Nazek Rehan (PWA), and Eng. Keith Brooke, Norplan.

Present from left: Eng. Basim Sirdah (Norplan/CEP), Mr. Keith Brooke, Eng. Farid Barood (Handala Company), MR. Tahseen Deyab (Handala Company), Eng. Majed Bahar (Consultant from EMCC, Al Rasheed Street), Eng. Ashraf Al Masry (Al Farra company), Eng. Ayman Funga (Ministry of Public Works), Eng. Ahmed Kullab (PWA), Eng. Mohamed Khalaf (CMWU).

the inspection teams Shallow trench using JVC. R33
Trench compaction between manholes  
Excavation works in R33. Project Manager Keith Brooke inspecting trench
 
  Manhole leveling at R35



Inspection of PVC pipes:
13th June 2016

 

Construction material arriving and ready for inspection.





TABULAR CONSTRUCTION PROGRESS - street number (RXX, See Road Map)
.

Area :
green= included;
white: not included

Street number Status started
green= started

Status
Green = Completed

  R01    
  R02 By October 2016 By October 2016
  R03 By October 2016 By October 2016
 

R04

   
  R05 By October 2016 By October 2016
  R06 By October 2016  
  R07    
  R07A    
  R08    
  R09    
 

R10

   
  R11 By October 2016 By October 2016
  R11A By October 2016 By October 2016
  R12 By October 2016 By October 2016
  R13    
  R14 By October 2016 By October 2016
  R15 By October 2016 By October 2016
  R16 By October 2016 By October 2016
  R17 By October 2016 By October 2016
  R18    
  R18A    
  R19    
  R19A    
  R20 By October 2016 By October 2016
  R21 By July 2016  
  R22    
  R23    
  R24    
  R25    
  R26    
  R27    
  R28    
  R29 By July 2016  
  R30    
  R31    
  R32    
  R33 By July 2016 By October 2016
  R34 By October 2016 By October 2016
  R35 By July 2016 By October 2016
  R36 By July 2016  
  R37    
  R38    
  R39 By July 2016  
  R40 By October 2016 By October 2016
  R41 By October 2016 By October 2016
  R42 By October 2016 By October 2016
  R43 By October 2016 By October 2016
  R44 By July 2016 By October 2016
  R45    
  R46 By October 2016 By October 2016
  R47    
  R48 By October 2016 By October 2016
  R49    
  R50    

 